2025
Baltimore Aircoil Italia S.r.l.
Chiuro, Sondrio
The client needed extending an industrial machine, operation, which made it necessary to remove a portion of the prefabricated structure to obtain the required space.
In a first phase it was defined the area to be removed e sono stati individuati i pannelli prefabbricati da sezionare. Successivamente sono stati eseguiti fori negli angoli per evitare sovrattagli, seguiti dai fori per i punti di imbrago, indispensabili per garantire il sollevamento sicuro delle porzioni di struttura.
The individual portions were then removed piece by piece, with the blocks sectioned according to the maximum load that can be lifted by the telescopic lifting machine.
The materials removed were loaded onto lorries and disposed of properly in landfills, ensuring maximum operational safety and responsible waste management.